Repair of hydropower station turbine casings to a tight deadline
BackgroundAs part of a contract with First Hydro, Kvaerner Boving undertook an on-site Engineering Critical Assessment of the spiral casing of turbines at Ffestiniog Power Station. Defects were found in 2 units, which required repair within the maintenance outage period. ObjectiveKvaerner Boving were required to project manage the removal of the defects and the completion of the repairs within 10 days ApproachTWI were contracted by Kvaerner Boving to provide assistance and technical support in undertaking the following:
BenefitRepair completed in 8 days allowing First Hydro to return the 2 units, each capable of generating 90 MW of electricity, to full and unrestricted operation within the outage period ConclusionUse of personnel with broad welding engineering and industrial experience enabled the repairs to be completed within the outage period, with decisions being taken on-site in real time. Copyright ©2004 TWI Ltd | ||
|
Information and advice from TWI and its partners are provided in good faith and based, where appropriate, on the best engineering knowledge available at the time and incorporated into TWI's website in accordance with TWI's ISO 9001:2000 accredited status. No warranty expressed or implied is given regarding the results or effects of applying information or advice obtained from the website, nor is any responsibility accepted for any consequential loss or damage.
| ||
|
|