Lead-time halved in heat exchanger production

Background

A central heating boiler manufacturer needed increased manufacturing efficiency to improve competitive position.

Objectives

  • to optimise layout of factory
  • to reduce manufacturing lead time

Approach

  • to gain understanding of issues affecting lead time and capacity
  • to build simulation of layout and test 'what if?' alternatives
  • to assess alternative layouts and rank quantitatively

Benefits

  • rapid comparison made of ~30 alternative layouts
  • release of £525,000 capital from inventory and WIP
  • lead time reduced from 9 to 4 days
  • safer, more organised working environment

Conclusion

Simulation identified routes to significant efficiency improvements

Copyright ©2004 TWI Ltd

Search for related content 
Information and advice from TWI and its partners are provided in good faith and based, where appropriate, on the best engineering knowledge available at the time and incorporated into TWI's website in accordance with TWI's ISO 9001:2000 accredited status. No warranty expressed or implied is given regarding the results or effects of applying information or advice obtained from the website, nor is any responsibility accepted for any consequential loss or damage.