Downtime reduced after Ethylene plant assessment

Ethylene plant
The owner/operator of an ethylene facility in North Africa needed an assessment of the 10-year old plant so that a future inspection strategy could be developed. TWI was called in to plan and execute the work.

The first phase involved two engineers visiting the plant for a week to review inspection records, NDT equipment, QA systems and to have discussions with key personnel. One important aspect of this visit was to identify previous failure mechanisms, consider other potential failure mechanisms and draw up an inspection list of vessels and interconnecting pipework in the high pressure envelope, cold blow down system and storage tanks. As a result of their findings, a new set of NDT procedures was written for the client.

The second visit coincided with a planned shutdown and included two engineers and three NDT technicians. The site team inspected the critical components using a combination of magnetic particle/dye penetrant, ultrasonic flaw sizing, site metallography and hardness surveys. More standard NDT was carried out by a contractor.

As defects were detected, the engineers were able to make fitness-for-purpose evaluations using TWI staff at Abington with engineering critical assessment (ECA) expertise. Further, where the defects were considered unacceptable, repair and renovation techniques were developed and implemented.

Other failed components were returned to TWI, where structural and materials engineers were able to investigate the causes of failure and recommend alternative materials or designs. TWI then made recommendations on future inspection strategy, training of plant inspectors and replacement/repair of equipment.

In addition, it was concluded that the time between planned shutdowns could be safely extended from two to three years.

The estimated value of the increased production obtained as a result of the reduced shutdown frequency was $1m/year.

Copyright © 2001, TWI Ltd

Information and advice from TWI and its partners are provided in good faith and based, where appropriate, on the best engineering knowledge available at the time and incorporated into TWI's website in accordance with TWI's ISO 9001:2000 accredited status. No warranty expressed or implied is given regarding the results or effects of applying information or advice obtained from the website, nor is any responsibility accepted for any consequential loss or damage.