Lead-time halved in heat exchanger production

Background

A central heating boiler manufacturer needed increased manufacturing efficiency to improve competitive position.

Objectives

  • to optimise layout of factory
  • to reduce manufacturing lead time

Approach

  • to gain understanding of issues affecting lead time and capacity
  • to build simulation of layout and test 'what if?' alternatives
  • to assess alternative layouts and rank quantitatively

Benefits

  • rapid comparison made of ~30 alternative layouts
  • release of £525,000 capital from inventory and WIP
  • lead time reduced from 9 to 4 days
  • safer, more organised working environment

Conclusion

Simulation identified routes to significant efficiency improvements